Power developer for Oracle's New Mexico campus gives up permit deadline

Project Jupiter's buildings are already up, but the fuel-cell plant meant to power them now depends on a state review regulators say they cannot time, with a governor-elect promising a pause on large data centers.

  • HEADCOUNT Newsroom
  • 4 min read

The company building the power plant for Oracle's planned $165 billion data center campus in southern New Mexico has surrendered the date that would have forced state regulators to rule on its air permit. Yucca Growth Infrastructure waived its right to a Nov. 23 decision, Bloomberg reported, and joined the New Mexico Environment Department on Nov. 3 in a motion asking the hearing officer to vacate the Dec. 7 public hearing. The motion, as described by Organ Mountain News and Voltgrid News, sets no new hearing date and no deadline for the state's technical review.

Project Jupiter is being developed by Oracle for OpenAI near Santa Teresa in Doña Ana County. Its two halves are now running on different clocks. The data center buildings do not need the same air permit, and construction on them has advanced. The natural gas-fed Bloom Energy fuel-cell plant that would power them cannot move without it. Searchlight New Mexico has reported that the buildings already put up remain without power. Oracle's plan for the campus remains 2028, Engineering News-Record reported in September.

The waiver is a reversal. In an Oct. 23 filing, Yucca said it had not waived the deadline and "should not be required or requested" to do so, according to Bloomberg. The deadline fell 180 days after the state's Air Quality Bureau ruled the application complete. To keep the Dec. 7 hearing, the department had to send its public notice to newspapers by Nov. 3, and it said it needed more time to review revisions Yucca submitted in October. That left the regulator having to approve or deny the permit to meet the developer's statutory deadline, Bloomberg reported. Yucca gave up the deadline shortly after. The same motion also says the bureau will not seek denial or dismissal of the application without a finding under the state's air-quality rules.

The revisions reopened the review. On Oct. 15, Oracle and Yucca proposed an enforceable cap on the fuel cells' operating output that, according to Oracle's announcement, would cut permitted emissions by about 35% and projected greenhouse gas emissions from about 8.8 million to 5.7 million tons a year, with the campus's planned IT capacity unchanged. Yucca has told regulators it intends to build the plant's full 2,462-megawatt nameplate but operate no more than 1,600 megawatts, a cap the state has not approved, Voltgrid reported. The proposal followed correspondence in which updated modeling doubled earlier estimates of concentrated pollutants, alongside a 2% rise in emissions, the Albuquerque Journal reported. The department noted the concentrations remained within federal thresholds, but an Air Quality Bureau lawyer, Brian Yardman-Frank, wrote in an Oct. 2 email that "the new modeling calls into question whether the original use of assumptions is a defensible and conservative approach."

The companies call the October changes refinements. New Energy Economy, a Santa Fe environmental group, calls them a substantial redesign. Hearing officer James O. Browning, a retired federal judge, rejected the group's bid to dismiss the application in late October; it filed a renewed motion to dismiss on Nov. 4 and opposes vacating the hearing without dismissal. Browning had not ruled on the joint motion by the morning of Nov. 5, when Organ Mountain News reported it could not verify an order granting it. A department spokesperson, Drew Goretzka, told Searchlight New Mexico the agency cannot estimate how long its review will take, citing its iterative nature.

That open end now runs into a change of government. Searchlight reported that the decision may slip into the new year, after Gov.-elect Deb Haaland takes office; Haaland has said she plans a first-day executive order pausing large data-center development. Jefferies analysts led by Julien Dumoulin-Smith wrote that the moves shift Bloom's largest disclosed project into 2027. "With no hearing date, the timing now depends on NMED's review pace and a new state political backdrop," they said. That is the analysts' estimate, not a schedule from Oracle.

Another approval path sits outside the air case. The Energy Transfer pipeline meant to carry gas to the plant has also faced regulatory obstacles, Bloomberg reported.

The financial pressure around the date is already visible. Oracle served the developer a force majeure notice in September, a clause that could let it delay payments if the campus misses its 2028 start, The Inference reported. The same outlet reported that a $25 million slice of Project Jupiter debt is among roughly $500 million of data-center loans being auctioned by an unnamed holder, and that the site's $18 billion of loans were quoted at 89 to 91 cents on the dollar in September. Oracle told Bloomberg it looks forward to moving efficiently toward a hearing and expects the department to treat its application "with the same fairness it has afforded countless other applications approved with similar or higher emissions levels over the past months and years."

The developers also face scrutiny over jobs. Doña Ana County has issued a new breach notice to the Project Jupiter developers, with commissioners citing missed job reports, according to the Albuquerque Journal.

  • Oracle
  • Project Jupiter
  • Yucca Growth Infrastructure
  • New Mexico
  • data centers
  • air permit
  • Bloom Energy
  • OpenAI

Sources (12)

  • bloomberg.com

    bloomberg.com/news/articles/2026-11-05/oracle-data-center-developer-waives-key-air-permit-deadline?leadSource=

  • organmountainnews.com

    organmountainnews.com/project-jupiter-air-permit-deadline-waived-hearing-delay-2026

  • voltgridnews.com

    voltgridnews.com/story/project-jupiter-air-permit-developer-waives-nov-23-deadline-seeks

  • theenergymag.com

    theenergymag.com/news/market-news/oracle-new-mexico-ai-delay-risk

  • oracle.com

    oracle.com/news/announcement/project-jupiter-microgrid-cuts-permitted-emissions-by-35-percent-2026-10-15

  • wire.fusion-42.com

    wire.fusion-42.com/stories/ea2bf1be-9fe1-40e9-ae6c-14d3158c4139

  • energyconnects.com

    energyconnects.com/news/gas-lng/2026/november/oracle-data-center-developer-waives-key-air-permit-deadline

  • finance.yahoo.com

    finance.yahoo.com/energy/articles/openai-linked-oracle-data-center-185408562.html

  • abqjournal.com

    abqjournal.com/news/new-challenge-to-project-jupiter-air-permit/3143387

  • energyinnovationreview.com

    energyinnovationreview.com/2026/11/05/yuccas-delay-risks-project-jupiters-permit-fate

  • theinference.org

    theinference.org/article/oracle-s-165-billion-new-mexico-campus-permit-slipped-past-december-7-as-lenders-sell-the-debt

  • stocktwits.com

    stocktwits.com/news-articles/markets/equity/open-ai-linked-oracle-data-center-reportedly-faces-fresh-power-permit-delay-in-new-mexico/cNG1ALIR94m

HEADCOUNT reporting is evidence-backed and human-reviewed. Read our methodology, or send corrections to ryan@headcount.news.

Share

LinkedInX

More from Industries →

The Morning Brief is coming soon

The HEADCOUNT
Morning Brief.

Get on the list for HEADCOUNT’s weekday briefing on the business of work.

  • Weekday mornings, built from published HEADCOUNT reporting
  • Evidence-backed — every item traces to sourced coverage
  • The Signal: what the day's developments indicate for hiring

By signing up you consent to receive the Morning Brief by email. Unsubscribe at any time. HEADCOUNT does not sell subscriber data.