Energy Department's first oil and gas loan sends $480 million to 22 Gulf platforms
Arena's Project Elkhorn is expected to support 2,400 construction jobs and 400 operations roles, while a separate $2.5 billion private investment pays for drilling.
The Energy Department has closed its first loan for domestic oil and gas production: $480 million to a subsidiary of Arena Energy to bring 22 aging platforms off Louisiana back to work. The department and the company say Project Elkhorn will support 2,400 construction jobs and 400 operations roles. The department's own environmental review draws a narrower line around what the federal money buys. Future development drilling, routine operations, eventual decommissioning and separately financed onshore engineering and fabrication all sit outside the financed scope, Engineering News-Record reported.
The borrower is Elkhorn Offshore, LLC, a wholly owned Arena subsidiary formed to own and reinvest in the infrastructure serving the company's Southern Eugene Island fields, about 170 miles southwest of New Orleans. According to the announcements Arena and the department's Office of Energy Dominance Financing issued on Nov. 10, the loan will pay to retool, refurbish and repower platforms, return idled ones to service, expand production and water-handling capacity at active facilities, and build gas pipeline to tie future wells into existing lines.
Arena produces about 30,000 barrels of oil a day offshore today, the department said. At peak, Project Elkhorn is expected to add up to 38,600 barrels a day and up to 77 million cubic feet of gas a day. The project is expected to more than double the company's rate of oil production, The Advocate reported, and will build or refurbish 450 miles of pipeline and allow Arena to run a second drilling rig. The federal loan covers 80% of the project, according to the newspaper.
The money arrives in stages. The financing is structured in five tranches extending through 2030, ENR reported. Arena's CEO, Mike Minarovic, told The Advocate the company will put up about $120 million over the next five years, with another $2.5 billion of private investment to pay for the drilling. By his account, the drilling capital is several times the size of the loan, and it is the part the department's review places outside the financed scope.
The case for a government lender rests on the gap private capital left. Energy Secretary Chris Wright, announcing the loan in Luling, pointed to a lack of private financing for drilling in the shallower waters of the continental shelf, despite ample capital for onshore and deepwater projects. "This is a loan that leads to development that otherwise would not happen or would happen at a much slower pace," he said. Banks are not interested in these aging assets, Minarovic said. Arena bought its Eugene Island assets from Chevron in 2016 and has drilled 26 wells there, and it has already spent about $30 million bringing decaying platforms back online after a previous operator shut them. "Then we had to invest in the infrastructure to get these things up and running again, because there was corrosion and there were a lot of issues," he said.
The lender has been newly repurposed. The office was rebranded last year after Congress eliminated a requirement that its loans support projects, such as wind and solar, that reduce greenhouse gas emissions, The Advocate reported. Greg Upton, director of energy policy at the LSU Energy Institute, told the paper that Gulf investment has shifted toward deepwater projects that "tend to favor larger companies," while this one "focuses instead on extending the productive life of existing shelf infrastructure."
The labor will move largely through Arena's own network. The company said it will execute the project with its long-standing affiliated partners, White Fleet Drilling and Rosefield Pipeline. At the Luling event, company officials put the new operations roles at 400 permanent positions, in a Gulf operation where Arena already has nearly 400 contractors, according to The Advocate.
White Fleet's equipment is part of the restart. White Fleet returned its WFD 450 jack-up to active drilling in Southern Eugene Island in late March after a $65 million acquisition and refurbishment program; the rig had been cold-stacked for seven years, ENR reported, citing Arena.
A development plan Arena Offshore LP filed with the Bureau of Ocean Energy Management in February shows what the work looks like at the level of a single structure. Platform D in Eugene Island Block 353, a two-deck, 20-slot platform Chevron installed in 1984 in about 296 feet of water, would return to active use, with two wells drilled from open slots by either the WFD 400 or the WFD 450. The platform would get a new well-test system, with liquids leaving through a proposed 10-inch pipeline and gas through a proposed 8-inch line, according to ENR's reading of the filing.
Sources (10)
Related coverage
The Morning Brief is coming soon
The HEADCOUNT
Morning Brief.
Get on the list for HEADCOUNT’s weekday briefing on the business of work.
- Weekday mornings, built from published HEADCOUNT reporting
- Evidence-backed — every item traces to sourced coverage
- The Signal: what the day's developments indicate for hiring