Amazon starts $7 billion Indiana data center with dedicated power plant due in 2030
Project Rise in Jasper County will have about 250 full-time jobs once built. Amazon’s NIPSCO service starts in 2027 and rises to 2,400 megawatts by 2032, with batteries and purchased capacity bridging the gap.
Amazon Web Services broke ground Thursday, Nov. 12, on Project Rise, a $7 billion data center campus in Wheatfield, Jasper County, Indiana. The campus will employ about 250 people full time once complete, The Times of Northwest Indiana reported.
The power plant intended to serve it is on a slower timetable. The gas-fired plant that utility NIPSCO’s generation arm is building next door is now expected to reach commercial operation in 2030, according to parent company NiSource’s Oct. 28 quarterly filing, as summarized by the energy newsletter Second Order.
Amazon has the land, the county tax agreement and a contractor on site. The plant meant to power its northern Indiana campuses is several years behind the concrete.
At the groundbreaking, Amazon and local officials described the construction scale. Ryan Construction is expected to employ hundreds of construction workers during a buildout that will take years, The Times reported. Wheatfield is one of three Amazon campuses in the region, alongside New Carlisle and Hobart, which together represent about $33 billion of investment and are expected to employ about 2,100 workers once completed. The New Carlisle campus, in St. Joseph County, is already half operational, according to the paper.
Second Order calculated that at about 250 permanent jobs, Wheatfield represents roughly $28 million of investment per job. A similar capital-to-payroll pattern appeared in Amazon’s expanded Louisiana investment, which grew from $12 billion to $18 billion and was announced with 2,250 construction jobs and 750 full-time positions, Newsweek reported in October.
The power arrangement explains why construction can start before the plant is ready. Indiana’s utility regulator approved a 15-year contract on June 17, 2026. Under that contract, NIPSCO begins serving Amazon’s Indiana data centers in 2027, and service rises to as much as 2,400 megawatts by the end of 2032, Second Order reported. The 2,400-megawatt figure covers Amazon’s data centers in NIPSCO territory as a group, not Wheatfield alone.
The filing describes the gas site as having its major permits. Its engineering contractor has full notice to proceed. Current work consists of site preparation, mass grading and civil works for the power block. NiSource characterizes the 2030 date as an optimization rather than a delay, according to the newsletter. The company’s earlier window for the full package was 2028 to 2032. Voltgrid News reported that the plant consists of two 1,300-megawatt units and that a NiSource executive said only one is moving to 2030.
Until the plant is running, temporary resources must carry the load. These include a 400-megawatt battery and a 100-megawatt battery under construction at the site, about $174.6 million of market capacity purchased for 2028 through 2030, and a 600-megawatt battery arrangement whose first phase is due by Dec. 1, 2027. These resources also serve NiSource’s other data center customers, Alphabet and Microsoft. NiSource expects those three customers to require about 4,920 megawatts at full ramp in 2032. Amazon begins paying a fixed capacity charge in January 2027, Voltgrid reported, about three years before the first gas unit is due.
Amazon’s commitment can still change in both directions. An amendment that would raise Amazon’s contract to 2,800 megawatts awaits an Indiana order, per Second Order. Separately, Amazon holds a one-time option, exercisable until March 31, 2029, to cut its commitment by 1,200 megawatts starting in January 2032. That reduction would be half the contract.
The Wheatfield site covers 304 acres and was sold to Amazon by NIPSCO. It sits a half mile from the utility’s R.M. Schahfer Generating Station, according to DCD, with up to nine buildings planned. The campus will mainly use air cooling and will need water only on the hottest days, around 2 percent of the year. NIPSCO plans to credit the land-sale proceeds to existing customers’ bills, The Times reported. Under the county agreement, Amazon will pay $98 million in taxes upfront and more than $700 million over 30 years. That includes $25 million to expand water access for the town of Wheatfield.
Indiana’s environmental regulator lists a draft air permit for Amazon Data Services in Jasper County. The public comment period ran through Nov. 16, after a virtual public hearing on Nov. 10. A second Amazon Data Services draft air permit, in Lake County, opened for comment on Nov. 13 and runs to Dec. 13.
Wheatfield, New Carlisle and Hobart fall under a $15 billion commitment Amazon made to northern Indiana in November 2025, when it said it aimed to add 2.4 gigawatts of capacity in the state. DCD reported that Amazon was also looking at Posey, Indiana, for another project earlier this month.
Amazon is also expanding in Northern Virginia. It has spent more than $170 million on land in Loudoun and Fairfax counties, according to the Washington Business Journal. The purchases include $99.79 million for a shuttered concrete plant at 44146 Wade Drive, where it aims to build a 100-foot data center, and $72 million for 13 acres on Hazel Park Court. Loudoun’s Board of Supervisors was scheduled to vote on Nov. 17 on a one-year pause on data centers, and a Virginia state senator proposed a three-year statewide moratorium earlier this year.
Sources (10)
Related coverage
The Morning Brief is coming soon
The HEADCOUNT
Morning Brief.
Get on the list for HEADCOUNT’s weekday briefing on the business of work.
- Weekday mornings, built from published HEADCOUNT reporting
- Evidence-backed — every item traces to sourced coverage
- The Signal: what the day's developments indicate for hiring